The Bentway and our construction partners Peter Kiewit Sons ULC and Waterfront Toronto want to alert local residents about increased construction traffic as we pour the concrete for our skating trail. The construction is dependent on good weather and will happen on Saturday, September 30. There will be multiple concrete trucks on site, resulting in increased traffic and noise along Fort York Blvd. There will be three pumping stations and flagmen at key access points. In order to maximize daylight the crew will start early in the morning. Please see the work schedule below:

6am-7am – Job Set-up
7am-8pm – Concrete placement and finishing. Use of concrete pumps for the placement of approximately 240 m3 of concrete
Following day – Curing of the concrete slab, no machinery

Please let us know if you have any questions or concerns. Residents can reach out to construction@thebentway.ca with any construction related inquiries.